Introduction
A good patio starts under the slabs, not on top of them. Whether you're laying paving slabs made from natural stone paving, including Indian sandstone paving, limestone paving, Egyptian limestone paving, granite paving or slate paving, or using 20 mm outdoor porcelain paving, the basics are much the same: firm ground, a properly compacted sub-base, the right drainage fall and a full mortar bed under every slab.
This is a practical UK guide to laying paving slabs on a traditional mortar bed. It covers the job from setting out to pointing, with the differences between natural stone and porcelain explained where they matter. It's aimed at everyday patio work, not driveways or specialist raised systems. If the ground is poor, the loading is unusual or the product has its own fitting instructions, the job needs to be specified accordingly.
On every full mortar-bed patio: Prime the back with a compatible bonding slurry and bed each slab fully. Dot and dab might look quicker, but hollow spots can mean loose or rocking slabs later.
Paving Slabs Laying Patterns
Decide on the pattern before you start. A good pattern can make a simple patio look right; a badly planned one can leave you with tiny cuts at the edges and joints that wander all over the place.
Single-size stone and porcelain are often laid in stack bond, running bond or third bond. Three-, four- and five-size natural stone packs are different: check the pack layout and count the slabs before you start laying.
| Pattern | Best suited to | Appearance | Main consideration |
|---|---|---|---|
| Stack Bond | Modern patios and accurately cut single-size paving | Formal, straight and structured | For a tidy grid, keep every joint straight and square. |
| Running Bond | Rectangular natural-stone or porcelain slabs | Balanced and less rigid than a grid | Plan the stagger so the edge cuts are sensible. |
| Third Bond | Long rectangular paving slabs | Contemporary with controlled joint movement | Offset each row by about one third of the slab length. |
| Mixed-Size Pattern | Mixed-size natural-stone packs and traditional patios | Natural, varied and informal | Use the correct pack diagram and watch the slab counts. |
Pattern note: The diagrams show the joint arrangement. Stone colour, texture and actual sizes may be different from the paving on your job.
How to Choose the Correct Laying Pattern
Start with the slab sizes you've actually got, the shape of the patio and where the cuts will finish. Neat, accurately cut slabs suit regular patterns. Mixed-size packs look better when the layout is planned rather than improvised.
- Go for stack bond when the slabs are accurately cut and you want a straight, modern grid.
- Use running bond for a simple staggered patio with rectangular slabs.
- Try third bond for longer slabs where a smaller offset looks better.
- Follow the pack diagram for mixed-size stone rather than making the pattern up as you go.
Dry-lay a few rows before mixing any mortar. Include the joint widths in your measurements and check the cuts along walls, steps and the outside edge. Moving the starting line by half a slab can save a lot of awkward cutting later.
Before You Start
Check the site conditions
Walk the site first. Check the doors, air bricks, drains, inspection covers, steps and any changes in level. Work out where rainwater is going before you set your paving height. Don't finish a smart-looking patio only to find you've covered an air brick or sent water towards the house.
Measure the area accurately
Measure the patio in metres. For a simple rectangle, length times width gives the square metres. Break an awkward shape into smaller sections and add them together.
Allow a bit extra for cuts and breakages. A straightforward patio might need about 10% extra; curves, diagonals and heavy cutting can push that to 12–15%. With a mixed-size pack, check the actual pack coverage and laying plan instead of guessing from the piece count.
- Allow around 10% extra on a straightforward rectangular patio.
- Allow roughly 12–15% for curves, diagonals and plenty of cuts.
- For mixed-size packs, check the total pack area and the supplied laying diagram.
Inspect deliveries before installation
Check the paving before laying it. Open and inspect the packs, look for damage and check that the sizes and finish match the order. Natural stone varies from slab to slab, so take pieces from different packs as you work. Porcelain is more consistent, but it's still worth checking the batch and shade.
Put aside any cracked or badly damaged pieces. A small chipped corner may be fine for a cut at the edge, but don't lay a slab you're not happy with and expect it to look better once it's pointed.
Materials and Tools
Natural Stone vs Porcelain: Installation Differences
The groundwork is broadly the same. What changes is how the paving behaves: how much water it absorbs, how accurately it's cut, which blade you need and what jointing or cleaning product will suit it. These are the points worth checking before the job starts.
| Paving material | Key installation consideration |
|---|---|
| Indian sandstone | Hand-cut and riven edges need room in the joints. Check thickness and use suitable slurry primer. |
| Egyptian or Indian limestone | Check porosity and finish. Keep acid cleaners away, and test any sealer first. |
| Granite paving | Heavy, dense slabs still need a full bed and good primer bond. Use a granite-rated blade. |
| Slate paving | Check the product is suitable outside and inspect any natural layers or splitting. |
| 20 mm outdoor porcelain | Low absorption means a compatible slurry primer is vital for wet-bed laying. Use the right porcelain blade and jointing product. |
Recommended Construction Build-Up
| Layer | Typical thickness | Purpose |
|---|---|---|
| Paving slab (natural stone or porcelain) | Usually 20 mm outdoor porcelain or roughly 20–25 mm calibrated stone; check the actual product | Finished wearing surface |
| Full mortar bed | Approximately 30–40 mm after compaction | Supports and levels the slab |
| Compacted sub-base | Often around 100 mm for a domestic pedestrian patio | Distributes load and limits settlement |
For an ordinary foot-traffic patio on suitable ground, the figures below are a useful starting point. They're not a one-size-fits-all specification. Weak or filled ground, heavy loads and vehicle traffic need a different design. Allow for the actual slab thickness as well as the finished levels and drainage.

1. Set Out the Patio
Mark out the patio with pegs and string lines. Check the corners and measure the diagonals if the job needs to be square. Use the actual slab size plus the joint when setting out; the size printed on the pack isn't always the exact working module.
Look ahead to the cuts at doors, steps, walls and outside edges. It's much easier to move a string line now than to cut a row of thin slivers later.
2. Establish Finished Levels
Get the finished levels sorted before you dig. Next to the house, the normal starting point is to keep the paving at least 150 mm below the damp-proof course (DPC), unless a properly designed threshold and drainage detail allows otherwise.
Keep air bricks and ventilation clear. Don't bridge the DPC with paving or mortar just to make the patio meet the door nicely.
3. Plan the Drainage Fall
A patio needs somewhere for the rain to go. For many domestic jobs, a fall of roughly 1:60 to 1:80 is a practical starting point. That's about 17 mm to 12.5 mm per metre. Check the surface finish and site conditions: rougher slabs and exposed areas may need particular care.
Set the high and low points with string lines or a laser. Fall away from the house towards a suitable drain, lawn or other designed outlet. Don't tip the runoff onto the neighbour's land.
Example: A 4 m patio needs about 50 mm of fall at 1:80, or 67 mm at 1:60.
4. Excavate the Area
Work back from the finished level. As an example, 20 mm porcelain on 30–40 mm of mortar and 100 mm of compacted sub-base adds up to about 150–160 mm. With 22 mm calibrated stone it's around 152–162 mm. The actual excavation will depend on the ground and the finished level you need.
Strip off turf, roots and any soft or loose material. If the ground underneath isn't firm, don't just put Type 1 over it and hope for the best. Get the formation right first.
5. Install Edge Restraints
An open patio edge needs proper support. Without it, the outer bedding can break away and the edge slabs may move. Use a suitable kerb, sett, brick edge or concrete haunch as the design requires.
Make sure the restraint is firm before you lay the main area, particularly where the patio finishes against a lawn or flower bed.
6. Lay and Compact the Sub-Base
Spread MOT Type 1 in manageable layers and compact it properly with a plate compactor. Don't tip in a big loose heap, rake it flat and call it done. For a nominal 100 mm compacted base, working in layers gives better control.
Follow the intended fall as you build up. Mortar is for bedding and fine adjustment, not for hiding a badly prepared base.
7. Dry-Lay and Blend the Paving
Lay a few slabs out dry to check the pattern, colours and joint widths. With sandstone and limestone, mix pieces from different packs so you don't end up with a dark patch at one end and a light patch at the other.
Check the face and the underside before each piece goes down. Riven and hand-cut stone can vary in thickness and edge line. Porcelain is more regular, but check the shade and make sure your chosen stagger is suitable for the format.
8. Prepare the Mortar
For a conventional domestic patio, a bedding mix of about 1 part cement to 4 or 5 parts sharp sand by volume is common. Add enough clean water to make a firm, workable mortar. It should hold together when you put it down, not run like soup.
Keep the mix consistent from batch to batch. Too dry and it won't compact and bond properly; too wet and you're asking for shrinkage, mess and possible staining. Follow the bedding-system supplier's instructions where a proprietary system is specified.
9. Apply Slurry Primer
Brush the dust off the back of the slab and prime the whole underside with a suitable bonding slurry just before laying. Don't miss the corners and don't let the primer dry out before the slab goes onto the fresh mortar.
This matters especially with porcelain. It takes up very little water, so ordinary mortar won't reliably bond to its underside without the right primer in a traditional wet-bed system. A compatible primer is also strongly recommended for natural stone. Keep slurry off the finished face.
A word on primer: A proper bond is important for natural stone and especially for low-absorption porcelain. Use the primer specified for the paving and bedding system, and lay the slab while the primer is still wet.
10. Lay the First Slab
Put down enough fresh mortar for a full bed and lower the primed slab into place. No dots, no rings and no deliberate voids underneath. The first slab sets your line and level, so take your time with it.
Tap it down carefully with a rubber mallet and check the fall with a long level. If it's badly out, lift it and reset the bed. Don't keep hammering one corner and risk cracking the slab.
11. Maintain Joint Widths
Don't use the same joint width for every type of paving. Rectified outdoor porcelain often works with joints around 3–6 mm where the manufacturer and jointing system allow. Riven or hand-cut sandstone often needs roughly 10–15 mm. Sawn stone can be tighter, depending on the product.
Use spacers where they help, but let the stone's edge tolerances guide the job. Above all, check the minimum width and depth required by the pointing or grout you've chosen.
12. Follow the Laying Pattern
Keep checking your lines as the patio grows. Stick to the chosen bond and, with mixed-size packs, keep an eye on how many slabs of each size you're using. Otherwise you can run out of one size before the job is finished.
Don't walk over freshly laid slabs or use them as a shortcut across the site. It's an easy way to move a slab and lose your fall.
13. Cut Slabs Safely
Use a blade made for the material. Porcelain needs a suitable porcelain diamond blade, usually a continuous-rim type or a good wet saw. Granite needs a granite-rated blade; sandstone, limestone and slate need blades suited to the particular stone.
Wet cutting or effective dust extraction is important. Stone, porcelain and mortar can all generate harmful dust when cut. Wear appropriate eye, hearing, hand and respiratory protection, and keep cutting slurry away from the finished patio.
14. Keep the Surface Clean
Clean mortar and slurry splashes as you go. Once cement has dried onto a riven stone face or textured porcelain, it can be a nuisance to remove. Use clean water and a suitable soft brush or sponge, without dragging gritty residue across the slabs.
Don't reach straight for acid cleaner. Limestone is particularly vulnerable, and acid can also attack cement joints. Only use cleaning products approved for the paving and jointing you've installed.
15. Allow the Bedding to Cure
Give the mortar time to set before you put traffic on it or start the next stage. Cold, wet weather can slow the cure, and heavy rain or frost can damage fresh work. Follow the bedding product's instructions rather than relying on a fixed number of hours.
Protect the patio where necessary, but don't leave covers sitting in a way that traps moisture or marks absorbent stone.
16. Joint the Paving
Choose the jointing product to match the slab, joint width, joint depth and bedding system. Some natural-stone patios are pointed with a suitable mortar or paving jointing compound. Narrow-jointed porcelain usually needs a grout or compound specifically approved for that use.
- Traditional mortar pointing: often based on cement and plastering or building sand, installed carefully without smearing the stone.
- Proprietary jointing compound: installed strictly in accordance with the manufacturer’s requirements for joint depth, width, moisture and weather.
Read the product instructions before you start. Some systems need damp paving; others don't. Don't put a skim of jointing material over a deep empty gap and expect it to last. Fill the joint to the required depth and clean the face as directed.
17. Clean and Inspect the Finished Patio
Before you pack up, walk the job and have a proper look. Check the joints, any chipped edges, the line of the paving, the drainage points and whether water is likely to sit in low spots.
Remove any remaining residue with the right cleaner for the material. A gentle water check can help show up poor falls, but don't soak fresh pointing before it's ready.
18. Sealing Natural Stone and Porcelain
Sealing is a choice, not an automatic last step. Some porous sandstone and limestone can benefit from a compatible sealer for easier cleaning, although it won't make the slabs stain-proof. Granite and slate need to be judged by their particular finish and the supplier's advice.
Outdoor porcelain normally doesn't need sealing. If you do seal natural stone, wait until the paving and joints are fully cured, clean and dry, and test a small area first. Some sealers deepen the colour or change the sheen.
Common Installation Errors
- Starting on soft ground or a poorly compacted sub-base.
- Dot and dab instead of a proper full mortar bed.
- Missing the primer, or leaving parts of the slab underside unprimed.
- Getting the finished level wrong at the DPC or air bricks.
- Not giving the patio enough fall, or sending water towards the building.
- Trying to correct a poor sub-base with a very thick mortar bed.
- Letting mortar, primer or grout dry on the slab face.
- Making the joints too narrow for the stone or the chosen pointing product.
- Walking on slabs before the bedding has set.
- Using the wrong cleaner or sealing damp paving.
Final Installation Checklist
- Ground and sub-base are firm and properly compacted.
- Finished paving level clears the DPC and all air bricks.
- Water falls away from buildings to a suitable outlet.
- Every slab is on a full mortar bed, not dots or rings.
- The correct slurry primer covers each slab's underside.
- Joint width suits the paving and pointing product.
- The chosen laying pattern still lines up properly.
- No loose or rocking slabs and no obvious low spots.
- Joints are filled to the correct depth.
- The finished face is clean and free of cement residue.
Paving Slabs Installation FAQs
How deep should I dig for a patio?
For a typical pedestrian patio on suitable ground, allow roughly 100 mm of compacted Type 1, around 30–40 mm of bedding mortar and the slab thickness. That is about 150–160 mm for 20 mm porcelain. Poor ground or heavier loads need a different build-up.
What mortar mix should I use for paving slabs?
A common traditional wet-bed mix is about 1 part cement to 4 or 5 parts sharp sand by volume. It needs to be firm and workable, not too wet. Follow the instructions for any proprietary bedding system.
Do I need slurry primer under natural stone and porcelain?
Yes, use a suitable bonding slurry over the full underside for this type of mortar-bed installation. It is especially important with porcelain because it absorbs very little water. Lay each slab before the primer dries.
How much fall does a patio need?
Around 1:60 to 1:80 is a common starting point for domestic patios, roughly 17–12.5 mm per metre. The right fall depends on the surface and the site. Always take water away from the building to a suitable outlet.
How wide should paving slab joints be?
Rectified outdoor porcelain often uses about 3–6 mm joints; hand-cut riven sandstone often needs about 10–15 mm. Sawn stone can be narrower. Always check the slab and jointing-product instructions.
Can I lay paving slabs over existing concrete?
Sometimes, yes, if the concrete is sound, stable, at the right level and properly drained. The bedding and primer must work as a bonded system, and existing movement joints need to be considered.
When can I walk on a newly laid patio?
When the bedding has set enough that the slabs won't move. That depends on the mortar and the weather, so follow the product instructions and don't rush it in cold or wet conditions.
Should I seal porcelain or natural stone paving?
Outdoor porcelain normally doesn't need sealing. Some porous natural stone may benefit from a suitable sealer, but it's optional. Let the paving cure and dry, then test a small area because sealers can change the colour or sheen.
Download Natural Stone Patio Laying Patterns
These four diagrams are for the natural-stone pack sizes shown, not a universal layout for every brand or for porcelain. Check the number and dimensions of the slabs in your delivery before following a pattern. The pictures are two across on desktop and one across on mobile.